The City of Bismarck city-wide street sweeping project is now complete. The Department of Public Works appreciates your cooperation during our sweeping efforts. Thank-you.
Reminders for Residents and Businesses
* Residents and businesses are reminded not to rake or blow leaves or grass into the street.
* Grass clippings plug our storm water system. Keep grass clippings out of the gutter line and street. Adopt an Inlet
| DATES | AREA | LOCATION |
| Apr 2-8 Completed | 1 | Century Avenue to Interstate 94 from State Street to West City Limits |
| Apr 8-11 Completed | 2 | Interstate 94 to Divide Avenue from East City Limits to West City Limits |
| Apr 12-22 Completed | 3 | Main Avenue to Bismarck Expressway from East City Limits to West City Limits |
| Apr 22-29 Completed | 4 | North City Limits to Century Avenue from East City Limits to State Street |
| Apr 29-May 6 Completed | 5 | North City Limits to Century Avenue from State Street to West City Limits |
| May 6-10 Completed | 6 | Bismarck Expressway to South City Limits from East City Limits to West City Limits |
| May 13-16 Completed | 7 | Divide Avenue to Boulevard Avenue and Highland Acres Area from East City Limits to West City Limits |
| May 16-23 Completed | 8 | Boulevard Avenue to Main Avenue from East City Limits to West City Limits |